Once you have made the decision to lien, you can sometimes find yourself out of luck. The general rule, as set out in Ontario’s Construction Lien Act, is that you have 45 days to place a lien (or “preserve the lien” in legal language) from the date of the abandonment of the contract or its completion. This general rule applies in cases where there is no certificate of substantial completion.